HOME PAGE | < Previous | Contents | Next >

1.3.2 INSTALLATION PROCEDURE


image

Before installing this optional unit:

Print out all data in the printer buffer.

Turn off the main switch and disconnect the power cord and the network cable.

You can add two more SG3 boards to this model. Follow the procedures for adding the single SG3 board installation or double SG3 board installation as the customer needs.


For Installing the single G3 Board

1. If the FCU is not installed in the machine, install the FCU (D167) in the machine first (page 1 "Fax Option Type M4 (D167)").

2. Remove the controller box cover [A] image x 4).


image

3. Remove the rear cover [A] image x 4).

image

4. Remove the "TEL2" [A] cover with a screw driver.

image


5. Install the SG3 interface unit [A] image x 3).

Insert the tab [B] of the SG3 interface unit bracket in the cutout [C] on the top of the controller box and the tab [D] of the controller box in the cutout [E] of the SG3 interface unit.

image

6. Attach one end of the flat cable [A] to CN603 on the FCU board and the other end of the flat cable [A] to CN660 on the CCU I/F board of the SG3 interface unit.

Make sure that the blue tapes of the flat cable face outward.


image

7. Reinstall the rear cover and controller box cover.

8. Attach the ferrite core to the telephone cord for single SG3 board installation.

9. Connect the telephone cord to the "LINE 2" jack for single SG3 board installation.

10. Connect the power plug to a power outlet and turn on the main power switch.

11. Enter the service mode. Set bit 1 of communication switch 16 to "1" (SP1-104-023).

12. Exit the service mode.

13. Turn the main power switch off and on.

14. Print out the system parameter list. Then check that "G3" shows as an option.

15. Set up and program the items required for PSTN-2 communications.


For Installing the Double G3 Boards

1. If the FCU is not installed in the machine, install the FCU (D167) in the machine first (page 1 "Fax Option Type M4 (D167)").

2. Remove the controller box cover [A] image x 4).


image

3. Remove the rear cover [A] image x 4).

image

4. Remove the "LINE2" [A] and "LINE3" [B] covers with a screw driver.

image


5. Remove the CCU I/F board and SG3 board [A] from the SG3 interface unit image x 6).

Do the same procedure as shown above for the second SG3 interface unit.


image

6. Remove the SG3 board [A] from one of the CCU I/F and SG3 board assemblies that you removed in step 5.

7. Attach the SG3 board removed in step 6 to the other CCU I/F and SG3 board assembly [B].


image


8. Attach the boards (CCU I/F board and two SG3 boards) to the SG3 interface unit bracket image x 6).

Use two screws from the six screws that were removed in step 5

image

9. Install the SG3 interface unit [A] image x 3).

Insert the tab [B] of the SG3 interface unit bracket in the cutout [C] on the top of the controller box and the tab [D] of the controller box in the cutout [E] of the SG3 interface unit.

image

10. Attach one end of the flat cable [A] to CN603 on the FCU board and the other end of the flat cable [A] to CN660 on the CCU I/F board of the SG3 interface unit.

Make sure that the blue tapes of the flat cable face outward.

image

11. Reinstall the rear cover and controller box cover.

12. Attach the two ferrite cores to the telephone cords for double-SG3 board installation.

13. Connect the telephone cords to the "LINE2" and "LINE3" jacks.

14. Connect the power plug to a power outlet and turn on the main power switch.

15. Enter the service mode. Set bit 1 of communication switch 16 to "1" (SP1-104-023).

16. Set bit 3 of communication switch 16 to "1" (SP1-104-023).

17. Exit the service mode.

18. Turn the main power switch off and on.

19. Print out the system parameter list. Then check that "G3" shows as an option.

20. Set up and program the items required for PSTN-2 communications.